OFF-GRID POWER

PHOTONS IN · RADIO WAVES OUT

Evvoia island · fully autonomous broadcast · decision history + live state

◉ CURRENT STATE

BUILD BLUEPRINT v7

2026-11-06 · audited freeze

The locked system: 3× DatouBoss 48V/314Ah on a shared bus, 4× BlueSolar MPPT 150/45 (non-Smart, RF hygiene), 3× Studer XTH 8000-48, combiner doctrine over the 30m run. String accounting, cable sizes, EMC implementation, build checklist.

OPEN BLUEPRINT
◌ ARCHIVE

BATTERY CHEMISTRY DECISION

2026-11-02 · superseded by blueprint v7

The original 20-year chemistry shootout: LiFePO4 vs NiFe vs Gel vs Flooded. Conclusion unchanged and inherited by v7 — only the vendor changed (Deye → DatouBoss). Kept as the decision record.

OPEN ARCHIVE
◉ LIVE

PLAN GAGE

2026-11-07 · six rungs · ENTRY → 👑 KING MODE

The load ladder gaged against the v7 fleet: daily kWh per rung vs same-day harvest, peak draw vs the 21 kVA Studer wall, bank autonomy when the clouds hold 30% light. Click a rung, the gage recalculates. Ladder law included: climb when the sky pays, drop a rung when it doesn't.

CLIMB THE LADDER
◉ READY

WIRING SCHEMATIC

v8.1 · 3 strings per MPPT · matches the buylist

One-page shared-bus topology: 12 PV strings → 4 combiners (gPV + SD63 + SPD) → 30m 25 mm² bundles → 4× BlueSolar 150/60-Tr → charge busbar; 3× DatouBoss packs → NH1/NH00 aR fuses → busbar; 95 mm² taps to the Studers. CRT-skinned SVG, v8.1 string accounting.

OPEN SCHEMATIC
◉ READY TO ORDER

SHOPPING LIST — BUYLIST v10.5

2026-11-12 · ~95% Greek · Phase 1

Phase 1 buy order matching wiring v8: 4× BlueSolar 150/60-Tr (checkout gate: SCC010060200, no Smart, no MC4), 8× ABB SD63 disconnects, NH00 80A aR leg fuses + NH1 250A aR pack backstop, Legrand 500A busbar, 25/95 mm² copper, earth kit. Supplier links, prices and open counter verdicts. PV combiner phase deferred, not skipped.

OPEN BUYLIST
◌ RESERVED

LIVE TELEMETRY

stub — lights up when the packs land

Reserved slot for real-time state: bus voltage, pack health, per-MPPT harvest, load profile, EMC sweep log. Will render from the Studer/MPPT data stream once the build is commissioned.

COMING ONLINE
◌ RESERVED

BUILD LOG

stub — first entry when copper hits the trench

Chronological build diary: orders, trenching, termination, SDR sweeps, commissioning days. The human-readable history of going dark-grid.

FIRST ENTRY SOON

SYSTEM STATE

Snapshot 2026-11-06 · updates as stages complete

BATTERY BANK: ORDERING MPPT FLEET: ORDERING COMBINERS: SPEC'D TRENCH: NOT STARTED STUDERS: IN SERVICE (LEGACY BANK) TELEMETRY: DARK

TARGET STATE — THE NUMBERS

What "off-grid" means for Avantida, quantified